New Pump Station and Tank Planned for Pleasant Valley Road
Cleveland Water is moving forward with plans to modernize critical water infrastructure in the southwest portion of its distribution system by replacing the aging Pleasant Valley Road Station. Through Emergency Ordinance No. 601-2026, the city will construct a new pump station and a ground-level tank to replace the existing facilities in Parma. This project is designed to ensure reliable water pressure for the Third High Service District, which provides water to several surrounding communities.
What's in the file
The ordinance authorizes the Division of Water to enter into professional service and public improvement contracts to design and construct a new pump station and a five million gallon above-ground tank. The project will also include the demolition and removal of the existing 1950s-era station and its underground concrete reservoir.
According to the 601-2026 Legislative Summary, the current underground reservoir is located at too low of an elevation, making it energy inefficient and difficult to operate. Replacing it with a higher-elevation above-ground tank is expected to improve operational efficiency.
The estimated project costs are broken down as follows:
| Item | Estimated Cost |
|---|---|
| Design | $2,000,000 |
| Construction | $13,000,000 |
| Total Project Cost | $15,000,000 |
The legislation also authorizes the Director of Public Utilities to employ professional consultants, acquire necessary rights-of-way, and apply for funding through Water Supply Revolving Loan Account loans or grants.
Who may be affected
- Division of Water / Department of Public Utilities: Tasked with managing the contracts, design, and construction of the new facilities.
- Third High Service District residents: Includes portions of Parma, North Royalton, Broadview Heights, Brecksville, Hinckley, Richfield, Richfield Township, and Bath who rely on this station for water pressure.
Status and timeline
The ordinance has passed City Council.
- May 7, 2026: Ordinance was introduced.
- Construction Phase: Expected to last approximately two years following the commencement of work.
Residents can verify these details by reviewing the official record for Ordinance No. 601-2026.
Source record
- File
- 601-2026
- Type
- Emergency Ordinance
- Status
- Passed
- Committee
- City Council
- Introduced
- May 6, 2026
Official documents
- 601-2026 PIK and Prof Serv Pleasant Pump Valley Station
- 601-2026 Legislative Summary
- 601-2026 Amend 601-2026
- 601-2026-as amended-desk copy-Final
- FINAL VERSION City Record July 24, 2026 - Page 25